Using Visual Studio Online, I've been able to create a backlog of work and put the relevant items in to the initial sprint. I'm the sole developer on this project and my time is limited. I've figured that within a 2 week sprint I could likely spend no more than 11 hours working on this project.
The initial sprint will run from Friday 14th November to Friday 28th November.
I first added the initial backlog items. These cover the ability to view a homepage, allow the user to create an account and allow the administrator to view and delete accounts.
The time available for the initial sprint is taken up by creating the homepage and create account functionality. I have split these down in to tasks, with time allocated to both development and research, where I lack knowledge.